Riverside Local committee re‑engages on Buckeye expansion and readies bond options
Summary
The Riverside Local Buildings & Grounds Committee reviewed plans for the Buckeye elementary expansion, confirmed the GMP for an eight‑classroom plus gym project has lapsed without financing, and instructed staff to pursue title work, insurance commitments and revised resolutions to enable bonds or COPS issuance.
The Riverside Local Buildings & Grounds Committee on Jan. 15 discussed next steps to restart the Buckeye school expansion after financing stalled and a guaranteed maximum price (GMP) was not executed.
Committee members and staff said there is an existing set of plans for an eight‑classroom addition, including a full‑size gym and stage, and that Cleveland Construction and architect Ryan are aware of the status. The GMP previously approved at a little over $8 million was not signed because district financing was not completed, leaving the project on hold.
Staff described potential ways to expand the scope cost‑effectively, including converting library space to classrooms or increasing the eight‑classroom plan to 10 classrooms without encroaching on…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat