Petersburg Assembly approves rezoning, supplemental budget changes and a generator contract; purchasing ordinance advances

Petersburg Borough Assembly · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At its Dec. 1 meeting, the Petersburg Borough Assembly unanimously approved a rezoning ordinance connected to the sale to Skylark Park LLC, passed a supplemental FY2026 budget (including $11,000 for ball-field repairs and $195,000 for downtown streetlight poles) and approved a design-build contract for the Scallabay generator; it also advanced an ordinance to permit electronic bid submissions to a second reading.

The Petersburg Borough Assembly voted unanimously on multiple formal items Dec. 1, approving a rezoning ordinance, a supplemental fiscal-year 2026 budget, and final contract form for a Scallabay generator design-build project, while advancing a purchasing-code update to its second reading.

Rezoning: The assembly adopted Ordinance 2025-14 on its third reading, which rezones Government Lot 21 to allow planned development and adjusts adjacent lots to create open recreational space in connection with a pending sale to Skylark Park LLC. The measure passed by roll-call vote with all members voting yes.

Supplemental budget: Ordinance 2025-15 (third reading) amended the FY2026 budget to reallocate $15,901.75 from the auto-meter reading capital project to the electric grid resiliency capital fund, budget $78,000 in revenue for the Banana Point Breakwater Improvement Project (per PIA resolution), appropriate up to $66,000 for engineering to prepare bid-ready documents for a wastewater outfall repair, budget $25,000 for a replacement variable-frequency drive at Pump Station 5, and appropriate $195,000 for new downtown streetlight poles (cash already reserved). The supplemental package also included $11,000 moved from P&R repair and maintenance to fix a bleacher roof and dugout at Mort Fryer Ball Field damaged in the Sept. 26 windstorm. Assembly discussion clarified that some small borough facilities are uninsured by choice and that staff will request quotes and follow up on insurance options. The motion passed unanimously.

Contract approval: The assembly approved final contract form for the Scallabay generator design-build contract with Dawson Construction Inc.; the borough previously awarded the contract in October and the approved design-build approach covers Phase 1 engineering with a later construction-price amendment to return to the assembly for approval. The motion passed unanimously.

Procurement ordinance: Ordinance 2025-16, which would amend chapter 4.04 of the municipal code to allow electronic submission of bids and proposals, was presented on second reading and passed the assembly on its second reading. Assembly members discussed that the change modernizes procurement practice and that electronic submissions are legally binding; the ordinance will require a third reading for final adoption.

Votes at a glance: Ordinance 2025-14 (rezoning) — passed (unanimous); Ordinance 2025-15 (supplemental FY2026 budget) — passed (unanimous); Ordinance 2025-16 (purchasing; second reading) — advanced (unanimous on second reading); Scallabay generator design-build contract (Dawson Construction Inc.) — approved (unanimous).

What’s next: Staff will follow up on quotes for the ball-field repairs and insurance options, and any construction-price amendment for the Scallabay generator will return to the assembly for approval; Ordinance 2025-16 requires a third reading for final adoption.