County facilities manager outlines boiler integration and backup‑generator fixes after October outage
Summary
Interim facilities manager Steve Davidson reported new courthouse boilers are installed but need Trane controls integration (estimated $20,800). He described October generator switch‑over failures, returning an older backup generator to service, and plans for networked push notifications and load testing.
Get email alerts on the Facility Maintenance topic
No spam. Unsubscribe anytime.
Interim facilities and maintenance manager Steve Davidson briefed the commissioners on several facility matters, including courthouse boilers, backup‑generator reliability, notification systems and snow‑removal logistics.
Davidson said the new boilers are installed and functional but not yet tied into the building automation system; he has scheduled Trane to perform the integration in January and estimated additional integration work at about $20,800. "They need to be tied into that system," he said, adding that without integration the boilers operate as single‑point units and cannot be monitored centrally.
He described an October event in which the new generator failed to switch over; the county's older basement generator was returned to service as an interim measure. Davidson said the county is working with PowerTech to add monitoring and push notifications so staff and the communications center will be alerted in real time if generators fail to start or transfer under load. He proposed regular load testing — including monthly runs with one run under load — and documentation of test results and notification procedures.
Davidson also reported the county purchased a pickup‑mounted snowplow (budgeted and paid) and discussed parking‑lot coordination during snow removal. Staff said they will pursue networked monitoring, schedule controlled load tests outside business hours where possible, and bring any required budget requests back to the board.
Next steps: Trane is scheduled for integration work in January; facilities staff will schedule load tests with notification to departments and confine testing to minimize service disruption.