Boone County council approves multiple highway bond appropriations for bridges, small structures and road conversions
Summary
Council approved transfers from bond cash balances to specific highway project lines, including $1,588,000 for two bridges and $405,000 for small structures, and approved additional appropriations across three bonds after brief staff clarification of advertised figures.
Get email alerts on the Capital Bonds topic
No spam. Unsubscribe anytime.
County staff explained that this funding action moves cash balances within existing bonds into project-specific lines so projects can be paid from the correct highway lines rather than from other properties.
Nick Bar (staff) told the council that total bond funds across the packages amount to $5,964,000 and that the requested appropriation for highway bond 49-31 is $1,588,000 to fund two bridge projects; an additional $405,000 was identified for small structures. Staff noted an apparent misprint in the advertised agenda numbers and clarified the corrected calculations during the meeting.
The council opened public hearings on each additional request (bond 49-31, 49-32, 49-33, bridge/small structures and road conversions). No members of the public spoke during the hearings. Each appropriation was moved, seconded and approved by voice vote.
Next steps: staff will finalize appropriation paperwork and proceed to allocate bond cash balances into the specific project lines as approved.