Board hears tank construction, well-project and storm-response updates; staff praised for emergency work

Coast Highway County Water District Board of Directors · January 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported progress on the Panga tank project, scheduled well drilling, and a swift emergency response during recent storms; directors credited field crews and contractors for restoring water service quickly, including generator work on Christmas Day.

District staff updated the board Jan. 13 on the Panga tank construction, other capital work and the district’s emergency response during recent storms.

Project staff said the Panga tank project was about 357 days into construction; recent work included interior installation of a 16-inch HDPE influent line, overflow panel, pipe supports and directional drilling for fiber communications. Staff said yard piping and finishing work remain and shared photos from inside the tank.

Operations staff summarized December maintenance: replacement of a PLC module at Denison associated with a panel failure, rebuild of a key PRV that serves North Hill flows, pump motor replacement at a booster pump, and mobilization of well-drilling contractors with drilling activities expected in late January or early February.

Directors asked about system flows and raw-water quality; staff reported sampling and monitoring are ongoing and noted system upgrades authorized in prior years improved reliability. Several directors commended staff for emergency response during the windstorm period—electricians and crews worked over the holidays to restore power and temporary generators, ensuring continued water service for affected neighborhoods.

The board accepted the operational updates and will continue to monitor project schedules and well-drilling milestones.