Bond 2022 update: new classrooms occupied, substantial completion targeted for March 2026
Summary
Construction representatives told trustees the Bond 2022 high‑school classroom wing is in use, the project is ~90% complete, temporary occupancy obtained for classrooms, and substantial completion is scheduled for March 2026 with athletic wing finishes and punch‑list items remaining.
Contractors and architects updated the Rockport‑Fulton ISD Board on progress of Bond 2022 construction work during the Jan. 15 meeting.
Teal Construction said the project is about 90% complete and staff have begun using new classrooms following receipt of a temporary certificate of occupancy for the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat