Keene committee backs agreement with Monadnock Conservancy, flags funding discrepancy
Summary
The committee recommended authorizing the city manager to negotiate an agreement with JRR Properties LLC and the Monadnock Conservancy to develop donated land and reimburse the Conservancy for stormwater work. The Conservancy asked for $234,845 but the motion text read $2,234,845; the committee voted unanimously.
Get email alerts on the Stormwater Infrastructure topic
No spam. Unsubscribe anytime.
The Keene Finance, Organization and Personnel Committee on [date not specified] recommended that the city manager be authorized to negotiate and execute an agreement with JRR Properties LLC and the Monadnock Conservancy to develop and accept donated parcel 567-001, Lot 2 and to reimburse the Conservancy for replacing the city's drainage infrastructure with a combination of an open swale and new stormwater pipe.
Tom Hanna, attorney with BCM Environmental and Land Law speaking on behalf of the Monadnock Conservancy, told the committee the project pairs a land donation—about 1 acre to the Conservancy and roughly 2.5 acres to the city for a park and playground—with construction of an open swale that will replace an aging storm pipe. Hanna said the Conservancy has contracted for work that costs about $269,000 and asked the city to increase its contribution to $234,845 to avoid a shortfall, citing updated inflation and construction-cost indexing since the city's 2019 CIP estimate.
Keene’s public works director (speaker 6) described the upstream network of open ditches and the rationale for an open-swale solution at this site, saying the city typically applies a 3% annual inflation factor to CIP line items but also reviewed construction-cost indices and found higher real-cost pressure consistent with Hanna’s request. The director said funds are available in the stormwater resiliency fund to support the reimbursement.
A motion presented by a committee member directed the city manager to negotiate and execute an agreement with JRR Properties LLC and the Monadnock Conservancy and to reimburse the Conservancy for replacement of drainage infrastructure “in the amount of $2,234,845” with funding to come from the stormwater resiliency program (the motion included a fund/code as read in the meeting). The committee voted unanimously in favor of the recommendation.
The record contains a numeric discrepancy: Hanna’s request and the figure he and staff repeatedly discussed in presentation were $234,845, while the motion text read $2,234,845. The committee vote adopted the motion as read; the difference was not resolved on the record at the meeting and is noted here for clarity. The motion also referenced a funding source from the stormwater resiliency program; the exact internal fund code was read aloud in the meeting but appears in the transcript as a partially garbled string and should be verified with city finance staff.
Hanna and staff highlighted non-financial benefits: the swale's ecological and educational value (potential collaboration with Antioch University New England), and flood-storage credits the city may allocate to developers or monetize. The committee recorded appreciation for staff's work and for the Conservancy’s role; the item will proceed to the full council as a committee recommendation.
What happens next: the committee recommended the authorization; the council is expected to receive the recommendation and consider formal agreement language and final funding details. The committee vote was unanimous.