Southgate board approves $349,420 pre-purchase of HVAC units for Anderson High School renovation
Summary
Contractors and district staff recommended pre-purchasing long-lead mechanical units to avoid 18–20 week manufacturing lead times; the board approved a not-to-exceed $349,420 pre-purchase and asked staff to present GMP and storage/security plans for early deliveries.
Contractors and district facilities staff told the board that several mechanical units for Anderson High School’s 2026 summer renovation are long-lead items and should be pre-purchased to avoid schedule delays.
Gary Kent of Plantman and RealPoint, joined by Mr. Hardy and representatives from Wakeley Architects and Chrisman Construction, recommended procuring the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat