Hampden boards weigh building repairs, energy storage sign‑off and a plan to repurpose Old Town Hall
Summary
Officials reported progress on a battery storage UL inspection and delays on an OPM contract for a municipal building project; the board also discussed forming a 7–9 person town hall repurposing committee and scheduled an invitation for interested applicants at next Tuesday’s meeting.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Officials used the Jan. 12 meeting to update the board on several facilities and infrastructure items, including a near‑complete energy storage inspection and plans to form a committee to study reuse of the old town hall.
Presiding official said he had been told by an Amaresco representative that 'the battery issue has been solved and is completely up and running at this point,' and town inspector staff reported receipt of comprehensive construction control documents and UL testing records that are under final review. Inspector Courtney is reviewing documentation to ensure UL and fire‑protection guidelines are satisfied before final sign‑off.
On the municipal building renovation, the fire chief and other staff reported delay on the owner’s project manager (OPM) contract: 'the town has been waiting 8 weeks on that one,' said a department representative. Board members said the original contract draft did not favor the town and that town counsel and staff had revised it to better protect town interests; staff will move the revised designer/architect contract through the review chain once the OPM contract is finalized.
The board also discussed repurposing the old town hall and vetted a list of interested residents for a committee. Members suggested a committee size of roughly 7–9 people, agreed to invite interested parties to the Select Board meeting next Tuesday at 7 p.m. and planned a public hearing for Bayberry Colony related items at the same meeting.
What’s next: Inspector review and finalization of battery and energy storage documentation; staff to advance revised OPM/architect contracts for signature; town to convene interested residents at the Select Board meeting to form the town hall repurposing committee.