Commission reviews hangar‑pad utility project and stormwater capacity changes
Summary
Staff reported progress on the hangar pad utility project, including site clearing, fencing and a stormwater quality/control study that recommends adding treatment structures; the project currently anticipates about 3,500 cubic yards of material for the immediate build and is moving through 90% design before pricing and bidding.
Get email alerts on the Hangar Development topic
No spam. Unsubscribe anytime.
Airport staff updated the commission on the hangar‑pad utility project, reporting site clearing, new security fencing and design progress toward a bid package.
Staff said a stormwater capacity and quality control study recommended adding quality‑control structures and modifying grading; the city asked for added controls that the airport plans to incorporate into the hangar‑pad utility project. A drainage basin created in 2004 was described as the key outflow for nearby development; staff estimated roughly 3,500 cubic yards of fill will be needed for the current phase and said some material could be reused onsite to improve low areas.
Design status and schedule: Barge (consultant) has completed an internal 90% review with a push to 90–100% on the drawing in the coming weeks. Staff said they expect a change order for the design-authority work authorization and will proceed to price the work after planning commission review. The airport will explore a city storm‑drainage fund to cover approximately $100,000 of storm drainage improvements so that tenant buildout funds are not reduced.
Facility details: Staff reviewed revisions to the building layout (smaller kitchenette, added data closet, ADA restroom and storage) and utility placement strategies including hiding HVAC units behind screening walls. Staff also said ongoing maintenance will be required for quality control filters and agreed to monitor them annually.
Next steps: Staff will complete the design review, obtain planning commission feedback, finalize pricing, and bring a bid schedule and any funding-parcel requests back to the commission.