Livonia to extend unit-price contracts for 2026 road and sidewalk programs; sidewalk assessments and final costs presented
Summary
Engineering recommended extending unit prices with Nagel Paving for the 2026 asphalt program ($3,806,939.15) and with Joe Rotondo Construction for sidewalk repairs; staff also presented final numbers for the 2025 sidewalk program and described 182 single-lot assessments totaling about $183,000 to be billed to property owners.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Livonia engineering division asked council on Jan. 14 to approve several public-works items and to waive formal bidding in favor of extending existing unit-price contracts.
Asphalt program: Staff recommended extending contract 25 unit prices with Nagel Paving to fund the 2026 asphalt program (contract 26-a) covering 22 street segments, with a cited contract amount of $3,806,939.15. Staff said the program is partly funded by a millage and highlighted corridor work on Harrison Street and related coordination with Wayne County work.
Sidewalks: For the 2025 sidewalk program (contract '25-g), engineering presented final contract figures reported in the transcript as $1,102,784.95 (with a closely placed but inconsistent figure also noted later in discussion); staff said roughly 182 single-lot assessments will total about $183,000 billed to property owners, and noted owners with bills above a threshold may work with the treasurer’s office on payment plans.
The department also requested authority to extend unit prices with Joe Rotondo Construction Corp for the 2026 sidewalk repair program and to appropriate funds to Precision Concrete Cutting Inc. Staff described prior-year under-budget performance for the unit-price approach and recommended returning to council with contract amounts in 2027 if necessary.
Why it matters: These programs cover routine but high-dollar maintenance work paid from millage and city budgets and may result in special assessments to property owners for sidewalk repairs.
What council did: Council members debated one-year versus two-year extensions for the sidewalk unit-price approach; staff said they will bring 2027 contract amounts back to council for approval. Multiple items were placed on the Jan. 26 regular agenda for formal approval, and staff will send assessment letters and follow the treasurer’s procedures for hardship accommodations.
Next steps: Items will be listed on the Jan. 26 regular meeting for formal votes; staff will provide final contract amounts and assessment mailing details as part of that packet.