Urbana Park District updates board on pavilion construction, Perkins Road and Phase 2 of Prairie/Weaver plan
Summary
Staff told the board Dec. 9 that the pavilion structure is up but masonry is delayed by weather; three change orders totaling $18,031 reduced contingency to $18,031, the contract stands at $973,054 and three pay applications totaling $275,000 have been processed. Staff also previewed Perkins Road site work and Phase 2 infrastructure and parking for Prairie/Weaver.
Staff presented slide photos and an update on ongoing capital projects at the Dec. 9 Urbana Park District meeting, noting construction progress, change orders and next steps for bidding and permitting.
On the pavilion project staff said the steel pavilion structure is erected but masonry work is delayed by winter weather. Staff reported three change orders: a pre‑construction DBE sourcing adjustment, an added light pole and a change of water‑fountain model, and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat