Airport staff schedules full-depth runway repair; estimate $150,000–$175,000, closure for about a week
Summary
Staff reported a full-depth repair is needed for a runway dip affecting multiple concrete panels; Comtech estimated the job at roughly $150,000–$175,000 and staff said the repair will likely close the runway for about seven days, with a NOTAM already entered and early-March reopening anticipated.
Get email alerts on the Runway Maintenance topic
No spam. Unsubscribe anytime.
Airport staff reported that a section of runway requires a full-depth concrete repair involving several panels. Comtech provided a price estimate in the range of $150,000 to $175,000, and staff said the work will likely extend runway closure by about seven days.
Staff said the repair will be scheduled during a slower month to reduce tenant impact; a NOTAM has been pre-inputted so the runway will automatically close on the scheduled date and is expected to remain closed until early March. Staff described a funding approach that would use expedited grant assistance and local contributions so each city’s share for this repair would be about $5,000. As staff put it, "for 175,000 ... it's gonna cost each city about $5,000 a piece." The board discussed the safety and operational risks of attempting limited runway operations during construction and several members emphasized that allowing aircraft movements while crews work would present an unacceptable safety risk.
Board members asked about cause analysis; staff and consultant said core samples had been taken and that the likely causes include subgrade or compaction issues from prior widening work. Staff committed to provide more technical details and core-sample results to the board once available.
The board expressed general support for repairing the section promptly and asked staff to provide the final cost, timeline and insurance/liability details once bids are opened.