Council authorizes up to $198,773 for Taylor Avenue waterline replacement
Summary
Council authorized the city manager to sign a public improvement contract (low bidder) to replace roughly 550 feet of asbestos‑cement waterline on Taylor Avenue for an amount not to exceed $198,773; the pipe will be replaced with ductile iron.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Talent City Council approved a public improvement contract at its Jan. 7 meeting to replace approximately 550 feet of aging asbestos‑cement (AC) water distribution pipe on Taylor Avenue. Staff said AC remains in roughly 14% of the city's distribution system, and the Taylor Avenue segment has experienced several significant leaks indicating imminent failure.
Staff explained that each repair to AC pipe weakens it further and that replacement is a prudent short‑to‑medium term action. The contract was awarded to the low bidder (contractor name appears with inconsistent spellings in the staff presentation and motion), and the council authorized the city manager to sign a standard public improvement contract for an amount not to exceed $198,773. Staff indicated the pipe will be replaced with ductile iron and the street will be repaved as part of the work.
Councilors asked questions about the annual AC replacement target (city target ~500 feet/year) and about pavement impacts; staff said the city has CIP line items and has pursued congressional directed spending in recent cycles but intends to chip away at the issue starting with logical problem areas such as Taylor Avenue.