Sandoval County outlines timeline to open new 911 dispatch center, schedules staff hiring and GIS cleanup
Summary
County and consultants gave an update on the Public Safety Answering Point (PSAP) buildout, saying a clean room and equipment installations are scheduled early in 2025, staffing recruitments will follow and a July 2025 go‑live remains the target. County and vendors also described a large GIS cleanup and broadband coordination effort to ensure rout
Sandoval County officials and outside consultants gave a detailed update on the county’s new Public Safety Answering Point (PSAP) during the county commission meeting, outlining a phased construction and technology rollout with a projected July 2025 go‑live.
Michael McGrady, principal of MCM Consulting Group, told the commission the PSAP facility is under construction and that the team expects to have a "clean room" finished in February 2025 so 911 and sensitive equipment can be installed. McGrady said vendor contracts for call‑handling equipment, logging recorders and radio consoles are in place or ordered and implementation work will begin in February with a kickoff meeting set for Feb. 10, 2025.
The project includes computer‑aided dispatch (CAD), records management (RMS), call handling, radio consoles and a logging recorder. McGrady said the team plans to migrate historical incident data from the county’s current system into the new county‑hosted server so prior alerts, medical…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat