Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Stamford planning board approves several developer- and WPCA-funded capital appropriations

Stamford Planning Board · November 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At its Nov. 5 meeting the Stamford Planning Board unanimously approved multiple supplemental capital appropriations tied to development conditions and WPCA needs, including traffic-signal and sidewalk work at Long Ridge Road and several sanitary and stormwater allocations for the Perna Lane project.

The Stamford Planning Board on Wednesday voted unanimously to accept several supplemental capital appropriations tied to developer commitments and WPCA reserve funding, clearing the way for traffic, sidewalk and sewer work and advancing the Perna Lane construction schedule.

The board approved a $250,000 developer-funded traffic-signal upgrade tied to zoning approval for 800 Long Ridge Road and a separate $250,000 fee‑in‑lieu payment to support sidewalks along Long Ridge Road. Both measures…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans