Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Regional Projects topic

No spam. Unsubscribe anytime.

State reports settlement for failed Southwest intake; NAWS filter underdrains to be replaced at manufacturer's cost

Water Topics Overview Committee · December 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

DWR reported a mediation settlement that returned about $12.4 million in cash for failed Southwest Pipeline intake attempts and said engineers are designing a new intake; at NAWS the Biota Water Treatment Plant's filter underdrains were found defective by a third-party review and will be removed and replaced at no cost, with substantial completion targeted by June 2026.

The committee received project-level updates for major regional water systems.

Southwest Pipeline intake: Rhys Haas said the Water Commission completed mediation with a contractor and insurers after three unsuccessful attempts to bore a new intake under Lake Sakakawea. The commission has received roughly $12.4 million in cash plus a professional-services credit and expects to move forward with preliminary engineering, alternative assessments (including whether the existing caisson can be reused), permitting with the Corps and Bureau of Reclamation, and a design-to-construction schedule targeting completion in 2030.

Northwest Area Water Supply (NAWS) and Biota Water Treatment Plant: Haas reported that the treatment plant's filter underdrains were judged defective by DWR's consulting engineer; the manufacturer resisted initial removal orders but agreed to a third-party review. The independent review supported the state's position; the manufacturer will remove and replace the underdrains at no cost and agreed to a schedule with substantial completion by June 2026, or the state will seek another contractor.

Haas also updated the committee on related West-zone Southwest project work (Buffalo Gap Reservoir milestone completion) and ongoing permitting and design work for intake alternatives. Committee members asked about prior expenditures on the intake attempts (about $28 million spent to date) and how settlement money would be applied; staff said settlement proceeds will enable the commission to move forward without protracted litigation and advance a new intake design and permits.