Board considers Draft Work Order 8 for US‑20 temporary road and storm sewer; FAA grant amendment cleared for contractor payment
Summary
Board reviewed Draft Work Order 8 (US‑20 temporary road and storm sewer final construction documents) and a grant amendment for a sealcoat project approved by the FAA on Dec. 19; motion to accept Work Order 8 was made but no vote outcome is recorded in the transcript.
Get email alerts on the Infrastructure Project topic
No spam. Unsubscribe anytime.
Emma Sanchez presented the airport development agenda items, highlighting Draft Work Order 8 — the remaining design work to move the US‑20 temporary road and storm‑sewer project from 60% to 100% design and into letting.
Sanchez asked board members to review the work order that had been introduced at the prior meeting and invited questions; a board member moved to accept Draft Work Order 8 and provided copies to staff. The transcript records the motion and that the copy was passed to board members for signature but does not record a subsequent voice vote or recorded outcome for the work order motion.
Sanchez also updated the board on three open grants, including a sealcoat grant for which an FAA amendment had been approved (email from Joe Edmond, Dec. 19). She outlined the paperwork steps: staff signature (Jessica), return to the FAA Airport District Office (ADO), and final inspection by FAA or staff before contractor payment is completed.
Sanchez described the fuel‑farm design approach (design‑bid‑build), noted the project will use IIJA funds, and said plans are expected to be ready to bid by March.