AGDC told the Legislative Budget and Audit Committee that the state retains a carried 25% ownership in the project under a joint‑venture structure with Glen Farm and will not provide additional funding through FID, but will continue to represent state interests and monitor adherence to project obligations.

Alaska Gasline Development Corporation officials told the Legislative Budget and Audit Committee the state maintains a 25% ownership interest in the Alaska LNG project after divesting operational control to Glen Farm.

Frank Richards, AGDC president, said AGDC moved project assets into a wholly owned subsidiary that was divested to a Glen Farm‑led joint venture (described in testimony as H Star/8 Star Alaska). As part of the transaction, Glen Farm agreed to lead project development and carry AGDC’s share through to final investment decision, meaning the state is not required to provide the near‑term construction funding but retains developer economics and tax benefits associated with its 25% interest.

Matt Kissinger of AGDC explained the commercial structure: the overall holding (8 Star Alaska) will own three project subsidiaries (gas treatment, pipeline, LNG facility) and as equity is raised in each subsidiary some ownership will be transferred to bring in outside capital. Kissinger said AGDC’s 25% was locked in at the 8 Star Alaska level, and AGDC will act as the state’s representative on governance matters and in negotiations to protect Alaska advantage principles.

When Representative Tim Josephson asked where earlier state expenditures and work products (engineering, permits and environmental analyses acquired in the TransCanada buyout) resided, AGDC said those assets were transferred to the state corporation and are being used by the current developer under the transition agreements.

Ending: AGDC officials said their role is now to advocate for Alaska interests while Glen Farm advances procurement and construction activity; AGDC emphasized it has reserved the state's rights and is monitoring milestones and compliance.