Goshen board clears path to bid on Patricia Boulevard renovation; Mark Cook timeline set
Summary
District staff told the board the Patricia Boulevard renovation will be advertised (current advertised estimate $1,056,000) with a pre-bid walk Nov. 20 and bid opening Dec. 5; board will consider bid approval Dec. 8. Mark Cook renovation has a later bid/opening schedule and an anticipated August completion target for classroom work.
Superintendent and facilities staff updated the Goshen Board on Nov. 10 on two capital projects and the district’s procurement timetable.
Administration said the projects represent about a $2,000,000 investment overall and that the bid package for the Patricia Boulevard site will be advertised with an advertised amount near $1,056,000. The board was told the advertised estimate equates to roughly $131 per square foot in one estimate presented during design review.
Key dates provided by district staff:
- Pre‑bid,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat