Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Renewable Energy topic
No spam. Unsubscribe anytime.
Board approves roughly $1.2 million change order for county solar installations at nine sites
Summary
County staff won board approval for a roughly $1.2 million change order to complete solar installations across nine county-owned sites, raising the project total to about $25 million while preserving projected long-term savings and eligibility for federal and state reimbursement.
Get email alerts on the Renewable Energy topic
No spam. Unsubscribe anytime.
The San Joaquin County Board of Supervisors voted unanimously Jan. 13 to approve an additional change order of about $1.2 million for ongoing solar installations at nine county-owned properties.
Josh Bronco, senior deputy county administrator assigned to capital projects, told the board the work originally budgeted in 2023 was estimated at $28.5 million. Contracts for steel fabrication and electrical work were awarded in 2024 for about $19.8 million, with another roughly $3.6 million set aside for solar panels and design, bringing the project budget to roughly $23.3 million. With the newly approved change order, Bronco said the total project cost is now expected to be approximately $25 million.
Bronco said the additional funds address greater-than-expected steel and welding needs to meet seismic-code requirements. He told the board most sites are complete and the county expects interconnection and permission-to-operate milestones by March 2026 to secure a near-retail reimbursement rate for exported energy; beyond that date, the compensation formula will shift and lower reimbursement. The county projects roughly $125 million in avoided utility costs over the next 25 years, including about $121.8 million in avoided PG&E bill costs and roughly $3.5 million in credits from selling excess solar power.
Board members asked how reimbursement flows back into county accounts; staff said funds will return to the county’s energy fund to support future projects. Bronco also said the county expects to be eligible to recover about 40–50% of construction costs under the Inflation Reduction Act, with reimbursements arriving in fiscal years 2026–27.
Motion and vote: A motion to approve the change order passed on a 5–0 vote.
Practical effect: The board authorized the additional spending within the project’s energy fund; staff said there is no impact on the general fund and appropriation exists within the energy budget.

