City approves $3.38M change order to add outdoor phase at Community Recreation Center
Grand Junction City Council
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
Council authorized a $3.384 million contract change order with FCI Contractors to add the Phase 1 outdoor facilities at the Community Recreation Center, funded by grants, interest income, sale proceeds and a $1 million private donation.
Council on Oct. 15 authorized a $3,384,053 change order to add Phase 1 outdoor facilities to the Community Recreation Center project, including a synthetic turf field, outdoor fitness turf, the Berkey Pavilion and temporary overflow parking.
Parks & Recreation Director Ken Sherbanow described the $3.8 million outdoor program…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans