Northrop Fire Station construction: steel arriving, drainage permit cleared, project running about 30–45 days behind
Summary
Project staff told the Building Committee that steel delivery is expected Dec. 29 with installation beginning Jan. 5; the site drainage plan received MassDOT approval but drainage construction is planned for spring; staff said the project is roughly 30–45 days behind original contract dates and that contract repercussions exist but have not yet been discussed with the contractor.
Project staff updated the Northrop Fire Station Building Committee on construction progress and near-term schedule changes during the Dec. 18 meeting.
The project representative reported that piers at the apparatus bay have been formed and poured, the stair tower and elevator are complete, underground drainage and conduits are in place and backfilled, and a mock-up wall and window…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat