Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Select Board hears updates on fire station project costs and negotiated change orders
Summary
The Fire Station Building Committee reported negotiated reductions to proposed change orders (PCOs) and described costs to date (about $1.1–$1.2M) including contaminated soil handling; members discussed clock and training‑tower design choices and commissioning services procurement.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Board members received an update from the Fire Station Building Committee at the Nov. 24 meeting about contractor proposed change orders and project costs. The committee and OPM negotiated with contractors over roughly $200,000 of proposed change orders; negotiations resulted in an accepted compromise of about $135,000 covering additional excavation and structural fill staging costs. The FSBC liaison said the town’s OPM advocated effectively for the town in those negotiations.
Committee reports indicated total project expenditures and obligations to date are in the $1.1–$1.2 million range, including the recently negotiated PCOs and contaminated‑soil handling; the liaison noted there is an additional unknown but nonzero amount of work remaining. Members asked for clearer descriptions and pipeline detail for other proposed change orders to improve transparency.
Design elements generated local debate: a clock proposed for the new station was estimated at around $20,000, while the training tower — justified as necessary for firefighter training — likely accounts for a substantially larger portion of construction cost and was described as likely to be 'more than half a million.' The committee also solicited commissioning services bids and recommended accepting a Colliers bid of about $49,000 for final building testing and commissioning, a figure well under the $150,000 line‑item budget for that scope.
The board asked the FSBC to include the FSBC summary in the record for public transparency and to provide more detailed PCO explanations in future reports.

