Board authorizes contract for new public‑safety CAD to replace 1999 system
Summary
Supervisors authorized the County Administrator to sign a contract to move the county’s CAD to a cloud‑based ProSuite (Central Square) system; staff said implementation will take about 15 months and the one‑time implementation cost is about $465,961 with an ongoing subscription fee.
Get email alerts on the Technology topic
No spam. Unsubscribe anytime.
Augusta County moved forward with plans to replace its longtime computer‑aided dispatch (CAD) system after staff presented a proposal for ProSuite (Central Square). Presenters said the county’s current CAD dates to 1999, is difficult to update and report from, and requires a labor‑intensive, manual process to extract information; the proposed package would include implementation, training and data transfer.
Staff estimated combined upfront costs for software, training and data transfer at about $465,961 and said the system would be cloud‑hosted with automatic updates and a subscription fee thereafter. The presentation noted interoperability benefits: the chosen vendor interfaces with records management (RMS), offers field‑ops mobile access and supports CAD‑to‑CAD grants that improve inter‑jurisdictional data sharing.
During Q&A, supervisors asked about vendor comparisons, participation in cooperative purchasing (TIPS), and yearly subscription increases; staff said detailed firm quotes require a full procurement process but noted a 5% discount available because the county already uses Central Square for records management. A motion to allow County Administrator Tim Fitzgerald to sign the contract as presented was moved and seconded, and the board voted to approve the action.
Staff said deployment would take roughly 15 months from contract and the project team will return with implementation milestones and appropriation details for subscription costs in future budget cycles.