School building committee says new high school construction came in under budget; Curtis Corner fields stay on separate $11 million track
Summary
A school building committee update said the guaranteed maximum price (GMP) for the new South Kingstown High School with Gilbane came in under the district's earlier budget target with savings of just under $2 million; the Curtis Corner athletic fields have a separate $11 million budget and will go out to bid separately.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Kate, representing the school building committee, told the School Committee the guaranteed maximum price for construction and demolition of the new South Kingstown High School came in under the figure the district had been using for planning.
Kate said the initial planning budget was $116 million and that the total contract value with Gilbane "came in at about $114.05 million," yielding a savings she described as "just under $2,000,000." She cautioned that the savings remain as contingency while work continues through the project schedule (the committee still has work to do through August 2027).
Kate also updated the committee on site progress: foundations are finishing and temporary roads are being installed for trucks; the steel vertical build was scheduled to begin on January 27, which will make the new building more visible beyond the perimeter fencing.
The Curtis Corner athletic fields were described as a separate budget item with an $11 million constraint; the project team is preparing construction documents to go out to bid to a contractor other than Gilbane, with the goal of opening facilities in 2027. Perdosa said demolition bids for Curtis Corner included both full demolition and options that preserve parts of the site so the project team could compare price points; no decision has been made about preservation.
Next steps: the project team will continue work on design and bid documents for Curtis Corner, monitor construction milestones for the high school and keep abutters informed about vibration and site‑development impacts.