Council awards $9.2 million contract for University Avenue area improvements Phase 2

Waukee City Council ยท January 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a public hearing, the council approved plan specifications for University Avenue Phase 2 and awarded the construction contract to Vanderpool Construction (Indianola) as the apparent low bidder at $9,198,722.55; the project budget is $12 million with major utility and roadway work and a paving interim completion date of Nov. 20, 2026.

Waukee โ€” City staff presented the Phase 2 design and budget for University Avenue area improvements, including South Warrior Lane and part of University Avenue, and the council approved plan specifications and a low-bid award to Vanderpool Construction for $9,198,722.55.

Rudy (staff) described the project scope as furnishing all materials, labor and equipment for construction of South Warrior Lane from Park Road to Broderick Drive and including about 1,000 feet of University Avenue and associated water-main installation to the new water tower. The project is included in the FY25โ€“26 capital improvements program with a total budget of $12,000,000.

After closing the public hearing with no written correspondence, staff presented four bids received and identified Vanderpool Construction of Indianola as the apparent low bidder at $9,198,722.55, roughly 16% under the engineer's estimate. Staff recommended awarding the contract, noting past satisfactory experience with the contractor on earlier projects; council voted to award the contract by roll call.

Key dates and scope: An interim completion date for paving, grading and utility installation was given as Nov. 20, 2026, with remaining restoration work expected complete by May 31, 2027.

Next steps: Staff will execute the contract with Vanderpool Construction and oversee construction, which includes grading, paving, utility installation and box culverts; project scheduling and coordination will follow established capital-project procedures.