Whitestown RDC approves first reimbursements for Wally’s and Paget Commons projects

Whitestown Redevelopment Commission · December 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Whitestown Redevelopment Commission approved first reimbursement applications for the Wally’s and Paget Commons developments, including a $2,170,236.35 invoice for Wally’s. Members discussed utility relocation delays tied to Duke Energy and approved both applications 3-0.

The Whitestown Redevelopment Commission voted Wednesday to approve the first round of infrastructure reimbursement payments for two major development projects, including a $2,170,236.35 invoice for the Wally’s project.

Todd Carlisle, serving as secretary and leading the meeting, said the Wally’s and Paget Commons applications are the first reimbursements against bond issuances and will have been reviewed by the town engineer and StructurePoint before coming to the commission. "The Wally's is yes. That total was, yes, $2,170,236.35," Carlisle said.

Commissioners discussed how much remains to complete the Wally’s project; staff referenced "4.7" as the remaining amount (discussed as a multi‑million-dollar balance). Sri, the town engineer, warned construction timing depends in part on utility relocations by Duke Energy, which can take 12 to 16 months in the town and could delay ground‑breaking and subsequent invoices.

Commissioner discussion emphasized that these are monthly reimbursement submittals and that more invoices are expected as the projects progress. A motion to approve application number 001 for Wally’s and the Paget Commons application passed 3-0.

The reimbursements are processed through the bond trustee and, as explained by staff, come to the RDC after engineering verification. Carlisle and staff said approved reimbursements will appear on future RDC agendas for confirmation.

The commission did not set a cap tied to the preapproval of bond-funded claims during this action; members said they would continue to monitor invoices as they arrive. The RDC will review future reimbursement requests as projects advance.