Bemidji board hears student concerns about high-school AC; district cites chiller hookup delays
Summary
Student representative and superintendent told the school board that a chiller installation delay prevented Bemidji High School air conditioning from working; trustees discussed long-term options for cooling older elementary schools and the budget implications of retrofits.
Get email alerts on the Facilities Cooling topic
No spam. Unsubscribe anytime.
A student representative told the Bemidji Area Schools board on May 19 that the high school’s air-conditioning project, originally targeted to finish May 1, has experienced multiple delays and left classrooms uncooled this spring. "The target for the AC project was over the year and projected to end on May 1," the student said, noting the impact on teaching and urging caution for students vulnerable to heat.
Superintendent Olsen told the board the work involves replacing large chiller units and that the new chillers have not yet been hooked up, making it impossible to turn the system on. "It's not a matter of shutting off the system — it's that we truly can't turn it on because it's not physically possible," Olsen said, and added the district will monitor temperatures and notify parents if conditions warrant.
Trustees used the discussion to broaden the conversation to older elementary facilities that lack central air. One member named Northern, J.W. Smith, Solway and Morris as buildings that routinely face warm conditions and said retrofitting them is "extremely expensive" and will require long-term planning such as bonding once other district debt is reduced. Another trustee cited regional climate projections and urged the district to incorporate cooling needs into capital planning.
Administrators framed shorter-term measures — drawing cooler night air and monitoring — as stopgaps while the district evaluates financing and sequencing for larger retrofits. The superintendent also said the district is continuing other scheduled capital work this summer, including LED retrofits and equipment replacements, as part of a broader facilities plan.
Board discussion did not produce a new funding commitment at the May 19 meeting; trustees asked administrators to keep the board and families informed as weather and installation progress dictate. The board adjourned after approving the evening’s remaining agenda items.