Council approved a subrecipient agreement obligating the City of Cudahy to contribute an estimated $9,668 annually (funded by Measure W) toward operations and maintenance for the regional John Anson Ford Park infiltration cistern project.
Get email alerts on the Stormwater Management topic
No spam. Unsubscribe anytime.
The Cudahy City Council approved a subrecipient agreement with the City of Bell Gardens to fund operations and maintenance for the John Anson Ford Park infiltration cistern, a regional stormwater project completed and operational in 2025.
Public Works Director Brial Diaz said the project was funded through regional collaboration, including a Proposition 1 grant and participation in the Gateway Water Management Authority (GWMA). The regional group identified the cistern as a high‑priority project; Bell Gardens will serve as the lead agency to prepare an annual budget and administer operations and maintenance for the useful life of the project.
The council was presented with the cost‑share methodology: the estimated annual project cost is $100,000; 50% ($50,000) is divided equally among seven member cities, with the remaining 50% allocated by watershed land area. Cudahy’s estimated annual share is $9,668, to be paid from Measure W funds.