Commission approves expanded scope for Ramsey County 4 soft‑spots repair, raising project cost
Summary
Commissioners approved a change to Ramsey County 4 pavement repair work after staff reported on missed quantity assumptions and material roll widths; the amended amount of $238,334.50 was approved.
Get email alerts on the County Road Projects topic
No spam. Unsubscribe anytime.
Ramsey County commissioners approved an expanded scope for repair work on soft spots along Ramsey County 4 after road staff said the original contractor estimate understated material quantities.
Road staff reported that initial bids had assumed a 12‑foot fabric cut but in the field contractors found fabric only supplied in 15‑foot rolls. That mismatch required changing cut widths and increased material needs. Staff presented three cost scenarios: leaving the original quantities (approximately $179,502), making a mid‑level correction (about $209,000), or widening cuts to match roll widths with an estimated total of $238,334.50. Staff recommended using the 15‑foot roll quantities rather than cutting rolls and wasting material.
Why it matters: the revision increases project cost but staff said funds are available from consolidated highway/FEMA money moved into the county highway fund, enabling the work while funding is on hand.
During discussion staff explained the discrepancy arose after ordering materials and discovering the fabric is now sold in 15‑foot widths, not 12 feet as bid. Bidders Paulson and Lakeside Gravel did not submit quotes because of the material‑handling needs. Commissioners agreed that, given the condition of the road and available funds, it was appropriate to fix the sections while money remains.
A motion to change the project to the revised quantities and length, and to approve the $238,334.50 total, was made, seconded and approved by voice vote; the clerk recorded the motion as carried.
Staff said the change will produce 15‑foot wide repairs on narrow sections and 28‑foot work on wider sections to accommodate overlaps in fabric placement. They noted the repairs will address the most damaged stretches but will not necessarily fix the entire length of Ramsey County 4. Staff will return with implementation details and scheduling information at a future meeting.