City provides progress report on park-bond projects, Little River trail work under way
Summary
Public-works staff reported grading and early construction activity on Little River linear trail and updates on Roots Creek and Buckhead trail connections; staff said right-of-way is in hand for several segments and described value-engineering work to control costs for the Buckhead Crossing.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
Staff updated the council on progress for projects funded by the voter-approved parks bond and related trail connections.
"We've made the largest parks and trails investment in our city's history," Mayor (unnamed) said at the outset; Mr. Borden from parks and public works gave the project-level briefing. He said grading for the Little River linear trail has begun and crews may pour concrete "in the next couple of weeks," with a target of completing an in-house trail connector by next summer, weather permitting.
Work on the Roots Creek Trail was described as moving into bridge recommendations following preliminary design review with Falcon Design; staff said right-of-way acquisitions have been completed for several segments. For the Buckhead Trail Crossing, staff rejected all bids earlier in the year and requested value engineering from Falcon Design to identify alternate routes or design changes to control costs.
Council members asked about schedules and environmental permitting; staff said wetlands and creek stabilization permitting have affected timelines for some segments but that design and phasing should allow progress without additional right-of-way needs.
Next steps: Staff will continue weekly coordination meetings with contractors and design teams, return schedule updates and advise council if revised budgets or further phasing are needed.