Port details Brannan Street Wharf: $26 million public wharf opening next week

Port Commission · July 9, 2013
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Port staff said the Brannan (Brandon) Street Wharf will be a 57,000-square-foot public space over water built to withstand seismic events and address sea-level rise; the $26 million project is funded through port capital, federal WRDA dollars, a parks bond and a coastal conservancy grant.

Port planners and engineers presented final construction and funding details for the Brannan (referred to in the presentation as Brannan/Brandon) Street Wharf, a new 57,000-square-foot public open space over the water between Piers 30'032 and Pier 38 that will include a large lawn, walkway with seating, an interpretive tide exhibit, and raised elements designed to provide sea-level-rise protection.

Project scale and cost: Project manager Steven Reel described the development as "a $26,000,000 project," with approximately $7,000,000 for demolition of the condemned Pier 36 and about $19,000,000 for construction of the new wharf. He told commissioners the funding package includes roughly $18.5 million in Port funds, $4.7 million in federal Water Resources Development Act funds, $2.9 million from the 2008 Clean and Safe Neighborhood Parks bond and a $100,000 California Coastal Conservancy grant.

Design and resilience: Reel explained the wharf's design-life goals (75 years), performance-based seismic design and measures to pick up 2' feet of elevation along key sections to address sea-level-rise exposure. The project team also installed seismic instrumentation and tailored construction sequencing to minimize impacts and complete demolition and pile driving on schedule.

Community and schedule: The Port said demolition began in March 2012 and major construction milestones have been completed; the commission was told the ribbon-cutting is scheduled for next week. The project also met local-business-enterprise and local-hire targets above initial goals (approximately 14% LBE and about 25% local hire overall on construction).

Budget status: Reel said the demolition and construction packages are within budget and that the construction contract remains under the 10% contingency; a planned float alternative was removed from the contract for lack of funding.

The presentation was informational and commissioners expressed enthusiasm about the public-space addition and resilience measures. No formal vote was required on the presentation.