Council approves contract amendment for lift station and force main; project cost now about $19.78 million
Summary
Castle Rock approved a second contract amendment and guaranteed maximum price for the lift station and force main project (Phase 1: 1.2 MGD). Staff said the negotiated construction GMP and associated easements bring the total project estimate to about $19.78 million; $14 million ARPA funding is available but the project requires an additional $984,296 to proceed.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Castle Rock Town Council voted unanimously to approve a contract amendment and guaranteed maximum price (GMP) for the city’s Lift Station and Force Main project, a phased regional wastewater project tied to Plum Creek Water Reclamation Authority that will initially deliver 1.2 million gallons per day capacity.
Town staff explained the project had been advanced under a progressive design‑build approach and a 60% design GMP had come in close to the town target; negotiations reduced contractor costs and staff recommended the GMP amendment with SJ Lewis Construction. Mark Henderson said the negotiated construction GMP for the contractor portion is roughly $16.766 million, with total project costs — including permanent and temporary easements, land acquisition and related items — estimated at about $19.78 million.
Funding context: the region has $14 million in American Rescue Plan Act (ARPA) funds designated to the project that must be spent next year; staff reported a remaining funding gap of $984,296 to reach the full project budget and said Douglas County agreed to cover trail easement costs. Staff recommended proceeding to avoid schedule delays that would risk ARPA eligibility and the council approved the amendment.
Why it matters: staff said proceeding now minimizes schedule and cost risk, preserves ARPA funding and will provide wastewater service to the Sedalia/Highway 85 corridor; the project will be built in phases with a second force main and additional pumps added if/when needed.
Outcome: Council approved the resolution to amend the contract and proceed with the GMP; staff expects design completion in early next year and construction to follow as soon as approvals are finalized.