Fitch Family Indoor Aquatic Center: contractors report steady progress, aim for March 2026 opening
Summary
Project managers told the council the aquatic center is largely enclosed, with pool tanks and mechanical systems advancing; they expect substantial completion Jan. 20, 2026 and a possible public opening in March 2026, and will report back Nov. 6 on south‑wall discoloration.
Get email alerts on the Fitch Aquatic Center topic
No spam. Unsubscribe anytime.
City staff and the project team updated the council on construction at the Fitch Family Indoor Aquatic Center. Brad Rodenberg (RDG) and Troy Turner (Story Construction) showed recent drone and interior photos documenting progress: precast exterior walls in place, curtain wall/glazing being installed, lap and wellness pool tanks poured and pool decks formed, and mechanical spaces prepared for filtration and boilers. Sitework images showed permeable pavers delivered and planting/bioretention cells being installed.
Substantial completion is currently targeted for Jan. 20, 2026, with staff estimating a possible opening in March 2026 after equipment installation and staff training. Council and the design team discussed visible discoloration and color variation on sections of the south‑facing precast wall; the team said they will provide recommended corrective options to the city by Nov. 6 and aim for a mid‑December solution if feasible. The council approved receiving the monthly update and thanked the project team for the pace of work.
The meeting record indicates the city and contractor will continue to coordinate on final exterior finishes and schedule details ahead of equipment installation and staff training planned after substantial completion.