Select and Planning boards agree to pause environmentally sensitive segment of BWALT Section 2

Westborough Select Board · November 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After staff said a MassTrails grant was not awarded and preliminary wetland reviews flagged potential impacts, the Select Board and Planning Board voted to pause development of the central portion of the Boston-Worcester ALl/Trail (BWALT) Section 2 from Otis Street to Milk Street and continue work on less-complex segments.

At a joint meeting Tuesday, the Westborough Select Board and Planning Board agreed to pause further development of a central, environmentally sensitive portion of the Boston–Worcester Alternate Trail (BWALT) Section 2, citing a failed MassTrails grant application, preliminary wetland findings, and uncertainty about the wastewater-treatment-plant expansion footprint.

Planning Director Jenny Gingers told the boards staff recommends strategic sequencing: advance the most feasible portions now while pausing the section that would require more extensive environmental coordination and an alternatives analysis. She said other projects — the Fisher Street Corridor (a MassDOT Safe Routes to School project with construction expected in 2028) and BWALT Section 1 work tied to the Otis Street Corridor — will maintain interim connectivity.

Board members and planning officials said the long-term BWALT alignment is unchanged. Select Board members noted that pausing the most complex portion did not reduce mobility objectives and would protect future infrastructure options, including potential wastewater-plant expansion. Members also discussed how advancing adjacent projects could strengthen future grant applications.

Both boards took identical formal action: the Select Board voted 5–0 to pause the portion of Section 2 from Otis Street to Milk Street and to continue work on other areas of Section 2; the Planning Board then adopted the same motion, 4–0. Staff will return with a scope and funding plan to address wetlands permitting, alternatives analysis, and environmental mitigation before resuming work on the paused segment.

What happens next: staff will continue design and grant-seeking for feasible segments, pursue environmental coordination for the paused area, and bring recommendations on alternatives and funding to the planning board and select board for future decisions.