Summary

Town engineer Brandy Nelson presented a 126‑page preliminary engineering report mapping parcels served by village water and recommending possible formation of two town water districts to align service with the town’s Traditional Neighborhood Development (TND). The board asked staff and counsel to follow up on legal agreements, village capacity, and

Brandy Nelson, the town’s contract engineer, presented a preliminary engineering report the board requested that maps parcels currently served by village water and outlines where the town might form one or two new water districts.

Nelson said the study—about 126 pages, with roughly 100 pages of data—was structured so the town could later re-use it for funding applications to the Environmental Facilities Corporation (EFC) if a capital project were proposed. "It's a two‑step process," Nelson told the board. "The first is to complete a preliminary engineering report, which is really just taking a snapshot in time of what we have so that we can then decide where does it make sense to form a district." (Brandy Nelson, Town engineer.)

The report identifies parcels north and south of Route 199 and along Route 9 that already take village water and highlights several discrete areas the consultant recommends for initial district formation: the Willow Park subdivision area on the east side of the village and a larger study area south of the village that includes the TND zones. Nelson said some parcels currently receiving water are connected under legacy or informal agreements; in other places water is provided by private easements. She noted the Glen Pond subdivision is served by a short main from the village well field and does not interconnect as a loop with the Route 9 main.

Supervisor Robert and several board members pressed Nelson on practical consequences. Nelson said the village has told consultants it currently has capacity and storage after recent upgrades, but that the town needs to confirm supply and operating responsibilities before forming districts. "Forming a district creates a governing entity," Nelson explained. "The other challenge that it creates for the village is that the village can't borrow money that benefits only town users." (Brandy Nelson, Town engineer.)

Board members asked whether the town should form narrowly drawn districts that include only parcels already served or create broader districts that include adjacent, unserved parcels to give the town flexibility for known future development in the TND. Nelson suggested the most straightforward first step would be to form districts that align with existing service and then consider extending mains tied to development proposals.

The board directed staff and counsel to: (1) work with village engineers and counsel to inventory and clarify any existing written or informal service agreements; (2) assess the village's firm supply and storage capacity and whether the village can reliably serve expanded territory; and (3) return with a recommended map and legal approach. Nelson offered to calculate a conceptual cost to extend a water main roughly 1,500 feet south on Route 9 as an example for discussion.

Next steps include follow‑up work with the town attorney and village staff, a mapping and capacity memo, and public‑notice steps required for any future district formation. The board did not take a formal vote to form districts at the meeting.