City staff reports sewer upgrades on track to free 190 ERUs; facility plan amendment must be adopted this year
Summary
City staff said work on the equalization basin is complete and remaining projects are on track for September 2026, which would unlock 190 equivalent residential units (ERUs). Staff warned the wastewater facility plan amendment and a preferred alternative must be adopted by the end of the year as part of the consent-decree timeline.
City staff provided a technical update on sewer capacity and the wastewater facility plan, describing recent construction milestones, schedule expectations and regulatory deadlines.
A staff member said the city recently finished the largest component of the scope—expanding the equalization basin at the treatment plant—and that the remaining projects should be complete by September 2026 to allow the city to request the next 190 equivalent residential units (ERUs). "We're on…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat