Parks staff told the Fallon (O'Fallon) Parks and Recreation Advisory Board on Nov. 18 that contractors have stripped fields A and B at Sports Park, are installing drains and lime stabilization, and expect substantial completion in mid‑April 2026; staff said stronger deposits will help secure out‑of‑area tournaments for 2026.
Get email alerts on the Parks Infrastructure topic
No spam. Unsubscribe anytime.
Parks staff reported significant progress on the turf installation for Sports Park fields A and B at the Nov. 18 meeting of the Fallon (O'Fallon) Parks and Recreation Advisory Board.
Bill, a parks staff member who presented the project update, said crews have stripped both fields A and B, installed stabilization material and begun placing drain pipes beneath the playing surface. “Once the lime and the soil dry, it becomes like concrete,” Bill said, describing why the team is using lime as part of field stabilization. He showed photos and said the contractor has been working long days to make up time lost to rain.
Board members asked whether the work covered only infields or full fields. Parks staff said fields A and B are being fully turfed; several other fields will receive infield-only work. The department listed a target of “substantial completion” in mid‑April 2026 and said it is already accepting tournament bookings for next year.
Staff said the turf installation is intended to reduce rainouts and attract larger, out‑of‑area tournaments that could increase local visitation. To reduce last‑minute cancellations, the parks department has changed its deposit policy for tournament reservations so groups forfeit a larger deposit if they cancel.
Project caveats noted by staff included weather risk: extreme frost or unstable ground can delay work, and opening fields too early can cause freeze‑thaw damage. Staff said contractors will take windows of workable weather and will pause work when frost prevents safe grading.
The parks report also noted smaller items of department business: a previously back‑ordered playground part for Dames Park has been installed and irrigation lines across the park system have been winterized.
The board did not adopt new policy at the meeting; staff said they will continue to accept tournament applications and will provide further scheduling details as the project approaches spring.