Madison County authorizes cost estimate for jail pod expansion and OKs nonbinding marketing of old jail
Summary
The Madison County Board of Commissioners on Jan. 6 approved a contract for a cost estimate to build out a jail pod and approved a nonbinding letter of intent allowing Jesse J. Wilkinson & Associates to market the old jail while financing decisions continue.
Get email alerts on the Detention Facility topic
No spam. Unsubscribe anytime.
The Madison County Board of Commissioners voted Jan. 6 to hire a consultant to estimate the cost of building out the final pod of the county jail and approved a nonbinding letter of intent allowing Jesse J. Wilkinson & Associates to market the old jail property.
Commissioners accepted a proposal from Studio View to perform the cost analysis that officials say is needed before the county decides whether to seek bond financing or use internal funds. The presenter said the firm’s work "will determine the cost" and that the estimate could be ready "within a month." The board approved the Studio View proposal by motion.
Why it matters: commissioners said a firm price is required to evaluate financing options and to inform next steps on the detention facility project. During public comment, Michael Garinger of Adams Township urged the board to produce supporting data before allocating taxpayer money, saying, "There wasn't a single metric in terms of how safe the project currently is...there wasn't any metrics presented about recidivism." David Sargent of Anderson, who said he had researched the plans and consulted the sheriff, told the board he supports the build-out, "for many different reasons."
What was approved: the nonbinding letter of intent gives Jesse J. Wilkinson & Associates the authority to market the old jail property until March; the document is explicitly nonbinding and, according to commissioners, intended to test interest from potential buyers while the new jail project advances. Commissioners also voted to approve a separate service agreement described in the meeting as an "MRI service agreement."
Next steps: county staff will receive the Studio View cost estimate and then present financing options, which county officials said they are developing with the county auditor and Baker Tilly. The letter of intent does not obligate the county to sell; it permits marketing activity while officials evaluate options.
Quoted: Michael Garinger told commissioners, "I object to that. I believe it deserves a proper evaluation of the current job site as well as how the prison is functioning now because you don't want to send taxpayer dollars to a job site that doesn't prove it's working the way it's supposed to be." David Sargent said, "The pod does need to be built out... I appreciate the commissioners for working to get this done."