Library staff described the Bountiful Branch restoration schedule and a temporary lease at 85 North Main, noting asbestos abatement, an anticipated April construction start, and accessibility and parking challenges for the off‑site location.

Library staff provided a detailed update on the Bountiful Branch restoration and the temporary location the system will use while the branch is closed for renovation.

Library Director Josh Johnson and branch staff described a sequence of near‑term steps: an asbestos abatement will occur before contractor mobilization, a large book sale and disposition of unwanted furniture will take place in the weeks before closure, and construction is slated to begin April 1. Staff said the last public day at the existing branch will be Saturday the 24th with the facility closed for business on the 26th. "We're hoping to open it mid February or early March; I expect it'll probably be closer to March 1," Johnson said when describing the target opening for the temporary site.

The board reviewed a proposed lease with Liberty Hills Academy for a temporary storefront site at 85 North Main. Staff walked board members through interior photos, egress and circulation, and logistics including delivery challenges from a rear stairway. Board members pressed staff on accessibility and ADA parking: a board member asked whether power‑assist doors and on‑street ADA stalls would be available. Staff said they are coordinating with the city and the fire marshal on occupancy, and that the city denied converting one Main‑Street stall to an ADA space; staff are pursuing other mitigation measures (designing entry flow, a possible doorbell for assisted entry, and parking in back).

Other operational matters include staffing assignments for the temporary site, moving shelving by the end of the month to enable remediation work, and exploring a second temporary location further south if budget permits. Staff also noted a new requirement surfaced in planning: a drinking fountain is required for the temporary occupancy and will be added to plans.

What the board decided: by voice vote the board ratified the lease with Liberty Hills Academy and authorized staff to proceed with move and permitting steps. Staff will report back on permitting, occupancy approvals, and operational readiness prior to the temporary opening.

Next steps: complete permits and fire marshal review, finalize deliveries and shelving placement, and confirm the temporary site opening date; construction mobilization is expected after asbestos abatement with an April 1 start to major work.