Dardenne Prairie staff seeks direction on TAP/STP projects; Town Square Boulevard to be submitted to MoDOT

Board of Aldermen, Dardenne Prairie · March 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff asked aldermen to prioritize TAP/STP grant submittals for February, reported final Town Square Boulevard plans will be submitted to MoDOT, and discussed a phased approach and multi-year timeline for Weldon Spring Road improvements with heavy outside match funding.

During staff communications, Speaker 6 asked the board for direction on Transportation Alternatives Program (TAP) and Surface Transportation Program (STP) grant priorities, noting that grant calls and submittal seasons come quickly in February and that preparing applications is time-consuming. "There's a lot of moving pieces as you all know with Weldon Spring Road," Speaker 6 said, and staff recommended breaking large projects into phases to improve chances for funding.

Speaker 6 reported final plans for Town Square Boulevard will be submitted to the Missouri Department of Transportation (MoDOT) this week and that, after MoDOT approval, the project could go out to bid within several months. Post Road design work is ongoing and staff have met with the property owner and Walmart to address right-of-way and easement issues.

On Weldon Spring Road, staff and aldermen discussed that phased construction—similar to the Post Road approach—is likely the only viable option, given scale and funding constraints. Speaker 6 estimated a 5–6 year process from design through completion, including right-of-way acquisition and easements, and emphasized that the city expects significant match funding from county partners (about a 90% contribution toward match in places). "It's from start to finish on something like Weldon Spring Road is probably a 5 to 6 year process," Speaker 6 said.

Board members asked staff to return with prioritized project lists so applications can be prepared over the holidays and early January, aiming to avoid last-minute panics during the submittal window.