Fountain Green trims CDBG scope to fund two pickleball courts after bids increase
Summary
Facing higher-than-expected bids, the council amended its CDBG request to prioritize two pickleball courts under the Bowery with lighting and removable posts; staff said a contractor quoted $193,320 for two courts and the city will pursue playground upgrades in a future funding round.
Get email alerts on the Parks Recreation topic
No spam. Unsubscribe anytime.
City staff told Council that bids for park improvements exceeded available Community Development Block Grant (CDBG) funds, and the city successfully amended its CDBG application to prioritize two pickleball courts under the Bowery rather than funding sand volleyball and immediate playground upgrades.
The presentation noted bids issued last month and said a contractor quoted $193,320 to install two pickleball courts with the specialized pavement and subsurface required for courts. Council discussed lighting (to allow evening play), removable posts so that other activities can still occur under the Bowery, and possible security-camera options. Staff said the city can reapply to CDBG in the future or pursue other funding sources to complete playground equipment and sand‑volleyball features later.
Council members asked for a timeline; staff expressed a goal of completing the courts this year if feasible, and noted that CDBG contracting and federal funding timetables could delay work. The council confirmed the project will include anchoring and planning details to avoid interfering with other park events. No ordinance action was required; staff will proceed with contract details and report back as procurement and scheduling are finalized.
Quotes from attendees and council emphasized balancing recreational demand with preserving park function during events.
Next steps: staff will finalize contractor agreements, explore lighting and security options, and track CDBG contracting timelines to minimize delays.