Council approves $378,706 award and agreement with Allred Construction for Carbon Avenue canal crossing
Summary
Price City awarded the Canal Crossing at Carbon Avenue contract to Allred Construction as the lowest bidder (about $378,700) and approved an agreement for $378,706 to complete the work; staff said six bids were received and two were below the engineer's estimate of roughly $425,000.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Price — The Price City Council approved a notice of award and an accompanying agreement for the Canal Crossing replacement at Carbon Avenue, awarding the project to Allred Construction as the lowest responsive bidder.
City staff said six bids were received, with two below the engineer's estimate (about $425,000). The council moved to approve the notice of award for the low bidder and then approved an agreement with Allred Construction for $378,706 to complete the work according to the city's design and specifications. Motions to award and to approve the agreement were both moved and seconded; the chair announced the motions carried by voice vote.
Staff noted the project will be constructed in winter when the canal has no water and cautioned that some traffic impacts are expected during construction. The contract award and agreement provide authority for staff to proceed with contractor mobilization and scheduling.
What happens next: staff will finalize construction scheduling with Allred Construction and execute the agreement; the project will proceed subject to standard permitting and winter construction constraints.