Town manager outlines phased community‑center plan and a standalone rooftop HVAC and generator push
Summary
The town manager said the community center fit‑out may be delayed to avoid overlapping library relocation costs; staff recommended moving a rooftop HVAC replacement now to capture a $500,000 Eversource rebate and pursue a grant for an emergency generator estimated at about $970,000.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The town manager updated the committee on the community center project and related capital options. He said the select board is considering delaying the full community‑center fit‑out until after decisions about the library’s temporary relocation are final. As a result, staff proposed advancing discrete, stand‑alone projects that would not complicate future phasing.
The manager pointed to three potential stand‑alone projects: replacement of rooftop HVAC units (to preserve eligibility for an estimated $500,000 Eversource rebate), parking lot and sidewalk repairs tied to a possible temporary library move to the lower level of the community center, and an emergency generator project for which the town had submitted a letter of interest for approximately $970,000 in grant support. He said the board will decide whether and how long to delay the overall fit‑out and that staff will refine costs and grant eligibility as timing becomes clearer.
Committee members discussed whether many of the items could be done piecemeal and whether advancing the rooftop HVAC work alone makes sense to capture the rebate. The town manager and staff said some items can be advanced independently, while others — notably work affecting internal building systems — are more interdependent and may need to wait for a coordinated phase.
No final appropriations were taken at the meeting; the manager said staff would return with additional detail once the select board clarifies timing for the full project.