Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Planning Commission backs Novak/NOVEC substation at former junkyard after applicant commits to buffering and use of existing transmission lines
Summary
The commission recommended approval of a Novak/NOVEC public facility review to build a substation at a cleaned‑up junkyard site on Sudley Manor Drive; staff said the industrial site, existing Dominion transmission poles and proposed screening make the location consistent with the comprehensive plan; the vote was 6–2.
The Planning Commission recommended approval of a public facility review for a Novak/NOVEC electrical substation at a former Novak junkyard on Sudley Manor Drive, finding the site consistent with the county’s comprehensive plan and electrical utility policies.
Jessica Pfeiffer of the applicant’s law firm said the ~19.3‑acre site is zoned heavy industrial and lies within the Data Center Overlay District. “This location was chosen because it allows for natural and additional screening proposed…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat