Folsom Streetscape reaches substantial completion in Phase 1; unforeseen utilities add $1.5M and a two-month delay

San Francisco Public Works Commission · February 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project manager Carol Huang said the $34.98 million Folsom Streetscape project has reached substantial completion for Phase 1 between 5th and 8th; unforeseen utility conflicts (including a high-voltage duct bank) and coordination with major events produced about $1.5 million in additional cost (under 5% of contract) and roughly a two-month schedule impact so far.

Project manager Carol Huang told the commission the Better Market Street phase 1 and the Folsom Streetscape project are progressing, and reported that the Folsom Streetscape contract was awarded for $34,979,747.50 with a 950-calendar-day construction schedule.

Huang said the contract includes a broad set of complete-streets improvements: a two-way cycle track, curb-ramp upgrades, sidewalk widening, a raised crosswalk, traffic-signal…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans