Fulshear authorizes $23.8 million expansion at Cross Creek Ranch wastewater plant

Fulshear City Council · November 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized an approximately $23.77 million contract Nov. 18 for a 1 million gallon-per-day Cross Creek Ranch wastewater reclamation facility expansion after staff described a competitive selection and value-engineering process; construction estimated at about two years.

Fulshear — The City Council on Nov. 18 authorized a professional services/construction agreement for an expansion of the Cross Creek Ranch Wastewater Reclamation Facility to add 1 million gallons per day of capacity.

Staff described the procurement as a competitive sealed-proposal process: two proposals were received, staff and the design engineer worked with the top-rated proposer to value-engineer the project and reduce cost. Staff presented the final project proposal as $23,772,675 and recommended Wharton Smith Incorporated be authorized to construct the expansion. Representatives from the firm were present for council questions.

The project is described by staff as the first step toward decommissioning the downtown treatment plant and is linked to several downstream pipeline and lift-station improvements in the city’s wastewater master plan. Staff estimated roughly a 24-month construction timeline once the project is kicked off.

Council action: a motion to approve the agreement (professional service/agreement 2025-040 as referenced in the packet) was made and carried by voice vote at the Nov. 18 meeting.

What council asked: members pressed staff on the value-engineering choices that reduced an earlier $27 million estimate, including consolidation of headworks and removal of an alternate clarifier and splitter box; staff outlined the specific items (headworks reconfiguration, removal of a clarifier and splitter box) and estimated savings tied to those changes.

Next steps: staff will finalize contract documents and begin preconstruction activities in coordination with the contractor and design team.

The financial and schedule details above are drawn from the staff presentation to council on Nov. 18.