City engineer recommends Burns and Jones as low bidder for Townsquare Avenue improvements, seeks 18.6% contingency

City of Dardenne Prairie Board (work session) · June 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city engineer recommended awarding the Townsquare Avenue Improvements construction contract to Burns and Jones Construction at a low bid of $674,000 and requested an 18.6% contingency (raising the requested contract authorization to about $800,000), noting the total with contingency remains under the $835,000 budget.

The city engineer told the board the Townsquare Avenue Improvements project (STP 5407) received five responsive bids and recommended awarding construction services to Burns and Jones Construction, the low bidder at $674,000. The project scope includes asphalt milling and paving from Mount Wing Haven Boulevard to the bridge crossing 360 and curb and sidewalk repairs.

Staff is also requesting a contingency equal to 18.6% of the contract amount to allow expedited approval of additional work related to unpredictable site conditions and utility conflicts. With the contingency included the requested authorization would be roughly $800,000, which the engineer said remains below the budgeted $835,000 for this project.

During discussion, a board member asked whether the plans address a local road hump; the engineer said the Townsquare project is primarily a mill-and-fill from curb to curb and that the hump removal would be part of a separate Post Road reconstruction project. Another member raised that prior projects (Stump Road) exposed unaccounted-for utility relocation costs, and recommended including utility-relocation contingencies in future grant estimates.

No formal construction contract was signed during the work session; the engineer requested two readings to keep the project on the funding schedule. The board assented to advance the item for ordinance consideration by voice vote later in the meeting.

Next steps: staff will prepare the ordinance and contract documents for formal consideration at the regular meeting and proceed with required grant and MoDOT approvals before construction.