City engineer recommends Asphalt Services LLC for trail crack-seal; Post Road Phase 1 design needs added box culvert funds
Summary
City Engineer Matt recommended awarding a crack-seal/trail repair contract for Bear Haven and Bluebird Meadow to Asphalt Services LLC after receiving two bids; Matt also said Post Road Phase 1 design uncovered a box culvert needing full replacement and staff requested a 10% supplemental grant from East West Gateway/the county to cover it.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
At the Nov. 19 Dardenne Prairie work session, City Engineer Matt presented two maintenance items: a recommended crack-seal contract for local trails and a supplemental funding request for Post Road Phase 1.
For trail maintenance, Matt said the city solicited bids for crack sealing on Bear Haven and Bluebird Meadow Trails and for limited trail replacement on Bear Haven where damage occurred. The city received two responsive bids: Burns and Jones at about $66,000 and Asphalt Services LLC at $37,900. Matt recommended accepting Asphalt Services LLC's lower bid, noting the work is specific to this year's needs and that the cost is slightly above budget so the budget could be amended later.
On the Post Road Phase 1 project, Matt said project designers inspected a box culvert during design and concluded it needs full replacement, which was not part of the original grant-funded scope. Staff requested an additional 10% from East West Gateway/the county to cover the additional cost and proposed a supplemental agreement to add the culvert replacement to the project scope.